Medupi shocker – Project leader quits, Eskom says “not a major concern”

roman crookesAfter interviewing Medupi GM Roman Crookes (right) last February, I was encouraged. Despite the heavy hemorrhaging of professional talent at Eskom – replaced by deployed cadres – all was not lost. Here was an engineer whose honesty instilled confidence. Despite the financial shenanigans, strikes and other disruptions, Crookes came across as a project leader coping well despite the curve balls thrown at him. So last night’s news that he has left “to pursue other interests” is disheartening. Even more so, Eskom’s spin that he won’t be missed. There is a massive difference between authentic leadership and simply giving someone a title. Dressing someone in a general’s uniform doesn’t automatically make them one. Eskom cannot afford to lose a leader like Crookes, especially not half way through such a critical project. Its board should have refused his resignation and moved heaven and earth to ensure he stuck around to finish the assignment. Or, if his departure was because of incompetence, to have spelled it out rather than letting a nervous nation assume the worst. – Alec Hogg

Cape Town – Energy analyst Chris Yelland on Sunday expressed concern over the resignation of Roman Crookes, project director at Medupi power station.

Yelland told Fin24 Crookes’ departure “obviously raises concerns about the institutional memory within Eskom as the engineering, procurement and construction (EPC) main contractor”.

Cranes sit beside the Medupi power station in Lephalale, as South African President Jacob Zuma arrives to open South Africa's first new power plant in 20 years, August 30, 2015. Construction on the six-unit, 4,764 MW plant was started in 2007 but the first 794 megawatts (MW) only came online this week after delays due to strikes, technical issues and cost overruns. REUTERS/Sydney Sheshibedi
Cranes sit beside the Medupi power station in Lephalale, as South African President Jacob Zuma arrives to open South Africa’s first new power plant in 20 years, August 30, 2015. Construction on the six-unit, 4,764 MW plant was started in 2007 but the first 794 megawatts (MW) only came online this week after delays due to strikes, technical issues and cost overruns. REUTERS/Sydney Sheshibedi

“One hopes that there will be a sufficiently experienced team at Eskom and at the Medupi site to ensure continuity and a smooth succession that will not result in any further delays,” he said.

Eskom spokesperson Khulu Phasiwe said Crookes’ departure is not a major concern for the state power utility as with any other project team there are other managers working very closely on the project and thus know what’s going on.

“There has also been a lot of cross pollination of experience and expertise between the teams at Medupi and Kusile,” which will make a “handover process seamless”, Phasiwe said.

Phasiwe said Crookes is the leader of a team of six managers from which a successor will likely to be named.

Read also: Medupi Timeline: Costs, delays spiralling – no completion in sight

“Roman has delivered the first 800 MW Unit into commercial service in August last year and leaves behind a strong and experienced management team who will continue to drive Medupi forward to completion,” said Phasiwe.

Crookes, who has been project director for the Medupi construction project from the beginning, will vacate his post at the end of January.

Crookes is leaving Eskom to pursue other opportunities, according to Phasiwe.

Yelland said the recent announcement on 24 November 2015 by Eskom CEO Brian Molefe of yet a further extension of the commercial operation date (COD) of Medupi Unit 5 to March 2018, and the COD for all 6 units to 2020, was a further signal that all was not going well on this project.

“Roman Crookes must have been under intense pressure.”

Medupi’s Unit 6 came into operation four years later than planned, but its 800 MW contribution to the grid has helped brought an end to load shedding which caused immense damage to the economy.

Yelland said it should be noted that the initial COD for all 6 units at Medupi was end 2013. “Several project delays and time over-runs have since extended this to 2020, making the project some 7 years late.”

Crookes told CNB Africa in an interview in February last year that if you look at Medupi as a construction project, “we’ve experienced the entire fleet of technical, commercial, construction and labour related challenges on this project so the delays we’ve seen have been cumulative, over a number of years”.

Read also: Hitachi bribery: Public Protector asked to probe Eskom’s Medupi tenders

“Obviously, Unit 6 is the one that we spent most of the time on, learning and developing all the facilities… we then take those lessons, distribute them throughout Medupi, and then do the same for Kusile.

“With the first one being now and the last one in 2019, our schedule shows that Unit 5, which is the second unit, will flow towards the end of next year/early 2017.  You’ll then start to see the lessons coming faster and the units between the gaps starting to come down and that’s how we’ll end off, in 2019,” said Crookes.

Phasiwe said Medupi Power Station is set to be completed by 2019/20, and Kusile in 2020/21.

Yelland didn’t want to take a guess at a possible successor for Crookes, but said “I’ll be keeping my ears close to the ground”. – Fin24

Source: http://www.fin24.com/Economy/Eskom/yelland-raises-concern-as-medupi-boss-quits-20160103

GoHighLevel
gohighlevel gohighlevel login gohighlevel pricing gohighlevel crm gohighlevel api gohighlevel support gohighlevel review gohighlevel logo what is gohighlevel gohighlevel affiliate gohighlevel integrations gohighlevel features gohighlevel app gohighlevel reviews gohighlevel training gohighlevel snapshots gohighlevel zapier app gohighlevel gohighlevel alternatives gohighlevel pricegohighlevel pricing guidegohighlevel api gohighlevel officialgohighlevel plansgohighlevel Funnelsgohighlevel Free Trialgohighlevel SAASgohighlevel Websitesgohighlevel Experts